Buying in a new building: building permit, commissioning document and preliminary contract

Under the Spatial Planning Act (ЗУТ) a building permit comes from the municipality's chief architect and a building cannot be used before commissioning. Upper categories need a use permit, lower ones a commissioning certificate.

Last reviewed:

The building permit and the start of construction

Article 148 of the Spatial Planning Act (ЗУТ) says buildings may be erected only if permitted under the Act. As a rule the permit is issued by the municipality's chief architect; for technical-infrastructure structures spanning more than one municipality and for structures of regional or national significance, the power lies with the regional governor or ministers. Article 157 treats as the start of construction the day on which the protocol opening the building site and fixing the building line and level is drawn up in line with the permit.

These two provisions turn into concrete questions to put to a seller: is there a permit, which body issued it, and has the site protocol been drawn up? The Ministry maintains a Unified Public Register of spatial planning on its website (Article 5a); the content and operation of that register were not examined in this reading.

Source: Spatial Planning Act (Закон за устройство на територията, ЗУТ) — current consolidated text on lex.bg (accessed 2026-10-09)

Commissioning a finished building

Article 177 requires the client to apply for commissioning once the building is finished. The application is accompanied by the final report, the connection contracts with the utility companies, the technical passport and the energy performance certificate of the new building, and it gives the cadastral identifier of the unit to be commissioned.

The document issued depends on the category of the building: for the first, second and third categories the bodies of the National Construction Control Directorate issue a use permit; for the fourth and fifth categories the body that issued the building permit issues a commissioning certificate within 7 days of the application. These documents are published in the unified public register.

Article 178 says buildings or parts of them may not be used before the competent body has commissioned them. Sixth-category buildings are outside commissioning. This list of documents is written for the client who builds; the law does not regulate what a buyer may ask for, and the list of questions below is a reading derived from the text of the law.

Source: Spatial Planning Act (Закон за устройство на територията, ЗУТ) — current consolidated text on lex.bg (accessed 2026-10-09)

Preliminary contract and transfer

Purchases made while construction is under way start with a preliminary contract. Article 19 of the Obligations and Contracts Act says this contract must be in writing, must contain the essential terms of the final contract and gives each party the right to bring an action for the final contract to be concluded; the transfer itself is made by notarial deed under Article 18.

The list of things to ask about, taken from this reading, for buying in a new building:

  • Is there a building permit, and which body issued it?
  • Has the site-opening protocol been drawn up?
  • What category is the building, and by which document will it be commissioned?
  • Are the utility connection contracts, the technical passport and the energy performance certificate ready?
  • Is the cadastral identifier of the unit known?

Source: Obligations and Contracts Act (ЗЗД) — current consolidated text on lex.bg, the lease chapter (accessed 2026-10-09) · Spatial Planning Act (Закон за устройство на територията, ЗУТ) — current consolidated text on lex.bg (accessed 2026-10-09)

Frequently asked

Can one live in a building that has not been commissioned?

The Spatial Planning Act says buildings or parts of them may not be used before the competent body has commissioned them.

Are a use permit and a commissioning certificate the same thing?

The law provides two separate documents depending on the category of the building: a use permit for the upper categories, a commissioning certificate for the lower ones.

Official sources

  1. Spatial Planning Act (Закон за устройство на територията, ЗУТ) — current consolidated text on lex.bg — accessed 2026-10-09
  2. Obligations and Contracts Act (ЗЗД) — current consolidated text on lex.bg, the lease chapter — accessed 2026-10-09

These articles are for general information only; they are not legal, financial or immigration advice — before taking any step, check the current text at the official source listed under each section. toBulgaria is an independent app: it is not an official application, service or endorsed source of the Bulgarian Ministry of Interior (МВР) or any other public authority.

Buying in a new building: building permit, commissioning document and preliminary contract · toBulgaria